they did the tests in the generators of the Villalonga wind farm



[ad_1]

Pending the announcement of the day of the official opening, the operational tests were carried out and the Villalonga wind farm, owned by the company Genneia, was put under tension.

Although there is still no specific date for the DOC (it is called at the beginning of the commercial operation), it is estimated that it would go into business in January. next year. The note will be made in the middle of next month.

In addition, it was pointed out by the company that the construction work would be completed four months earlier than planned in the contract. Work began in September 2017.

The Villalonga wind farm was the subject of a call for tenders during the first phase of the RenovAr program and has 15 wind turbines with a capacity of 51.75 MW. To this will be added the Villalonga II Park, whose energy will be destined for the private market (MATER).

The generators have a height of 87 meters between the ground and the center line of the rotor and consist of three shovels 66 meters long. They are connected by an underground network that will transport energy to a 33 / 132Kv transformer station.

The energy will enter the national system interconnected by the network AND Patagones-ET Pedro Luro.

It is located a few meters from the national road 3, between Villalonga and Stroeder.

It is the third wind farm commissioned in the region after the inaugurations of Ingeniero Mario Cebreiro (Pampa Energía, Bahía Blanca) and La Castellana (CP Renovables, Villarino).

[ad_2]
Source link