Power failure in Argentina: the supply of electricity in the country is standardized



[ad_1]

To integrate

We have already supplied 70% of the customers of our concession. The service will continue to be gradually restored in the coming hours. #Edenor

– Edenor customers (@EdenorClientes) June 16, 2019

According to the secretariat, "At present, the Salto Grande hydroelectric power plant is being progressively restored and the stations in the province of Buenos Aires, Entre Rios and Santa Fe, have been supplied with power. fed from the request of Uruguay, which cut with the Argentine system ".

To integrate

A few minutes ago, we reached 70% of the offer in our dealership. We continue to receive instructions from CAMMESA to take over the power of the system.

– Edelap (@EDELAP__Oficial) June 16, 2019

"The regions Whose center and country are in the process of standardization with the Los Reyunos and Los Nihuiles hydropower plants and other fast-moving thermal power stations in the region. In the region of Comahue, the standardization process is delayed due to inconvenience related to the startup of plants for standardization, "the statement added.

To integrate

The service had already been restored to 700,000 customers with the entrance of the district of Caballito. Standardization work is underway and could last all Sunday. https://t.co/boq8FzOKVv

– Edesur Argentina (@OficialEdesur) June 16, 2019

The agency also said that "at 10:45, about 2,000 MW of demand has been standardized, out of a projected total demand of 15,000 MW".

At 11:40, Edesur reported that "370,000 users" had retrieved the offer. barrack, Puerto Madero and Retirement they were the first Buenosairean neighborhoods to be refueled. And they continued, around noon, Belgrano, Palermo, Recoleta.

At the same time, Edenor indicated that the service was standardized Saint Isidre, Boulogne, Martinez, Loma Hermosa, San Martin, Tigre and Pilar, Las Heras, Hurlingham, February 3, Vicente López and La Matanza.

To integrate

The power-up process has already begun from the most powerful points of the system, the Yacyretá, Chocón and Salto Grande hydroelectric plants. Transener has opened the system and is powered up again to be able to regulate the service.

– Edenor customers (@EdenorClientes) June 16, 2019

Uruguay's National Administration of Power Stations and Transmissions (UTE) also confirmed on its Twitter account that "on 7.06, a fault in the Argentine network affected the interconnected network, leaving the entire national territory without service, as well as that several provinces of the neighboring Country.

.

[ad_2]
Source link