The installation of the main equipment and construction of buildings and facilities continues at the Sovetskaya Gavan Thermal Power Plant. According to the news agency "Khabarovsk Territory Today" in OAO "RusHydro", the specialists of the organization of contractors now install boilers No. 2 and 3.
– 14 contract organizations, more than 800 people and 60 equipment work every day on the site, RusHydro ". – Completion of all the erection work of the builders of objects by the end of next year. The launch of the station is scheduled for December 2019. Recall, the Sovetskaya Gavan power plant is called to replace the capacity of the obsolete May GRES. The new cogeneration plant will become a source of energy for the future development
The station will be equipped with an automated process control system. It is badumed that the installed electrical capacity of the new cogeneration plant will be 126 MW, the thermal power of 200 Gcal / hour and the annual electricity production of 630 million kWh