The repair schedule of the Ave World can be broken



[ad_1]

The contractor might not be able to repair the sidewalks of Mir Avenue in Krasnoyarsk before the August 25 deadline. The first deputy mayor of Krasnoyarsk, Vladislav Loginov, spoke about it during a briefing for the press

According to him, the delay was due to the late launch of the l '. Sidewalk tile production plant in Sosnovoborsk.

"According to our agreements, the factory was to produce the first production on June 21. But in fact, the first products went only this week.The delay of one month affected the working hours" , said Loginov.

According to him, the delay was attempted to compensate by providing rail transport Novorossiysk, but here because of logistics complex

"All these difficulties in the Materials supply suggests that delays may occur on some sections of the sidewalk, in some areas of the coverage.Today, 10 brigades are working at Mir Avenue.There are 15 people in the dismantling of cobblestones at night and about 80 people in the day when laying.As soon as the factory will start issuing more products, the number of employees will increase to 200. It's the normative number that will run all work schedules, "said Loginov.

[ad_2]
Source link