SÃO PAULO – The auction of electricity transmission lines that begins this morning (28) is already attracting a large number of interested people to the headquarters of the B3 in São Paulo. The wallet limited the entry of the general public into the space, only for today the qualified promoters of the 20 lots proposed.
The objective is to avoid the storage that was recorded at the last transmission auction, marked by long queues at the entrance of the building
The sale auction, conducted by the National Electric Power Agency (Aneel), will offer 20 lots totaling 2,560 kilometers (km) in transmission lines and substations with capacity
L & # 39; Regulatory agency estimates that badets represent a total of R $ 6 billion in investments, with the prospect of generating 13,600 direct jobs
Companies, located in 16 states, will have a duration of 36 to 63 months to enter commercial operation. The concessions granted are 30 years from the conclusion of the contracts.
Bidders who offered the highest rebate in relation to Aneel's maximum annual allowable income (RAP) will be due. In total, the PAR of the 20 lots amounts to 25.7 billion reais over the duration of the contracts
The lots will be presented in numerical order, from 1 to 20. In the case of more than 30,000 an interested party, if the difference between the lowest bid and the other proposals are greater than 5%, the one that gives the highest discount (the lowest bid) wins. If the difference is less than or equal to 5%, or in the case of a tie, the hands – free step will be opened, with lower bid turns than the lowest bid.
After the last batch, new offers can be received live -voice for lots that have not received offers in the first round.