The test of the cargo on the Hisgaura deck will take place on Tuesday, December 4 next | Local



[ad_1]

Email this page
Printer version

After several days of badysis of the technical report on the bridge Hisgaura on the Curos-Málaga road handed over by the audit office of ETA, the Fund for the adaptation, l & # 39; National Institute of Roads, Invías and the construction company Sacyr Colombia have concluded the loading tests of then enter the last stage of the work.

Read also: Is the Hisgaura bridge ready to perform the load test?

According to the Fund's communication from 21 to 28 November, the mathematical model, the load test protocol and the construction process of the Hisgaura bridge were examined. The technical group then commented on the load test protocol and requested that it be adapted to the maximum requirements of the standard used.

Similarly, "a series of technical requirements have been formulated on the submitted reports, some of which they have already been adjusted by the contractor and others are being processed ", says the document.

For the above, Sacyr will start the protocol approved by the supervisor for load testing from Tuesday, December 4th.

Read also: What are the progress of the construction works of Hisgaura builders in the country?