New phase of construction of a wind farm in Las Tunas



[ad_1]

Las Tunas.- More than 100 million 600 thousand pesos include in its investment plan the electric company of Las Tunas this year, much of which is intended to develop renewable sources of energy, reports the 26th digital. 19659002] It is already in the Carúpano Port Terminal, in the municipality of Puerto Padre, the first of three planned shipments of construction and badembly equipment for wind farms in the La Herradura region.

Cranes, harrows, drilling equipment, excavation and leveling of land are part of material imported from China, which did not exist in the country because of the large size required to undertake this task, which is taking place for the first time in Cuba.

Read more here: They prepare for Las Tunas force related to the construction of wind farms

According to Omilton Rodríguez Rivas, director of investments in the electric company of Las Tunas, af August, the first towers, ambulances and other components of the 54 wind turbines planned to be installed in the parks of La Herradura 1 and La Herradura 2 will begin to be received, also by the Asian giant.

The steel needed for the foundries of the bases is already in place of the site and began to move, from the quarry of Las Parras, to Majibacoa, the aggregate needed for the manufacture of concrete . The goal is to start digging and finishing the first bases at the end of July and closing the year with the first two circuits of each park, with an installed capacity of 10 megawatts each.

WITH THE FORCE OF THE SUN

In the coming days, he will complete his test phase and will connect to the National Electro-energetic System (SEN), the solar photovoltaic park Manatí 1, the second of the kind in the province, which will produce 2.2 megawatts.

At the end of July, the badembly work of Parada 2, located in Puerto Padre, which would begin its trial period for the production of 4.4 megawatts, the largest installed capacity eastern territory, should be completed. 19659003] The electric company of Las Tunas plans to build another site of this type before the end of 2018, called Manatí 2, in the municipality of the same name, which would bring to four the number of photovoltaic systems in operation here

Since September 2017, energy is delivered to SEN in Parada Park 1, whose operation has been deemed effective since it generates about 350 megawatts a month in its five hours of activity.

Manuel Alomá, director of the renewable energy sources of the UEB power plants, declared 26 that in the hours of greatest solar radiation intensity, 11:00 am morning at 1:00 pm, the park generated 2, 1 megawatt, very close to the installed capacity (2.2 megawatts) which confirms the reliability of the studies conducted.

By 2019, the East Balcon Electric Company plans to build three additional solar photovoltaic parks, two in Puerto Padre and another in "Amancio", in addition to continuing work in the La Herradura 1 and La Herradura 2 wind farms, and the preparation of a third in the Nuevas Grandes area, in the municipality of Manatí.

You will have Las Tunas in its north coast, the largest wind farm of Cuba (+ video)