Kumasi airport to be ready in October 2022 – For international travel



[ad_1]

Construction staff briefing President Nana Addo Dankwa Akufo-Addo during his visit to Kumasi Airport

Construction staff briefing President Nana Addo Dankwa Akufo-Addo during his visit to Kumasi Airport

Kumasi Airport is expected to be ready as an international facility will be ready in October next year when the ongoing expansion work is completed.

Currently, phases two and three of the works – which include a newly constructed terminal and a control tower – are 77 percent complete, according to Contracta UK CEO Fabio Camara, whose construction company is undertaking the project. enlargement.

A test of the installation is expected to begin in January next year with a view to preparing it by June.

President Nana Addo Dankwa Akufo-Addo said he was pleased with the extent and quality of the work so far when he arrived at the airport last Friday for a four-day tour of the Ashanti region. .

Phase II

The first phase of the project involved rehabilitation works of $ 29 million in December 2014, which involved the installation of aeronautical lighting systems on the ground and the rehabilitation of the existing runway.

Groundbreaking for the € 66.35 million ($ 75.23 million) second phase of the expansion project took place in November 2018, which includes the construction of a new passenger terminal and multiple service facilities at the airport.

The new terminal will have the capacity to handle more than one million passengers per year, while the existing runway is to be extended from the current 1,981 meters to 2,300 meters, allowing the airport to accommodate wide-body aircraft such than the Boeing 737-800.

Phase III

As part of the third phase, the scope of work is the development of an extension of the terminal, a new fire station, a new access road to the fire brigade and a new air traffic control tower.

Other facilities are the development of a 9,000 square meter parking extension, a 4,200 square meter access road extension and two new boarding bridges, while the scope of work on the side runway includes a 7,731 square meter apron extension, a 202,805 square meter runway extension and an airside service road.

Background

Construction of Kumasi Airport was approved in 1940 and operations began in 1943.

Airside operations at the airport were streamlined by the government with a series of development activities carried out on the runway between 1958 and 1959.

The airport underwent major renovations such as the installation of taxiway lights and the extension of the runway to the south during the 1970s.

The installation of another lighting system, the extension of the runway and the construction of a new terminal were completed in 1993 as part of a modernization project.

The airport served as a military base until its conversion to a domestic airport in 1999.