AS "Sadales tīkls" will invest 2 million euros this year in the regeneration of the district of Pieriga – Regions



[ad_1]

AS Sadales tīkls (ST) will invest 2 million euros this year in renewing the electricity grid of the Pieriga area – Marupe, Baldone, Olaine, Kekava, Salaspils, Stopinu, Ropazi, Ādaži. During the year, districts plan to restore 36 km of 17.6 km medium-voltage power lines to rebuild low-voltage power lines and rebuild or build 16 new transformer stations [19659002] In recent years, ST paid particular attention to renewing the electricity grid. population growth and business development. ST continues to renovate and gradually improve the electricity grid by increasing the reliability and quality of electricity supply of several thousand customers in the districts of Marupe, Baldone, Olaine, Kekava, Salaspils, Stopinu, Ropazi and Ādaži

The Marupe area is vast An overhaul of the electricity grid has already been carried out in previous years, but this year the reconstruction of the network is expected to continue on Daugavas Street, where the reconstruction of the ST road will destroy a power line. low voltage of 0.4 kV and will realize the construction of a new cable line. The work will take place from Memele to Avotu Street

The reconstruction of the Baldone district is from the place where the Ķekaviņa river crosses the A7 Riga-Bauska highway, up to the Strīķeri estate and the around Kāsuļuļi. In general, the average voltage of overhead power lines of 20 kV is renewed in this area at 8.7 km and the 4.9 km long power line is rebuilt in an isolated wiring line. After the rebuilding of the network, customers will reduce the number of power supply disruptions caused by the fall of trees and branches to overhead power lines, as well as the safety of economic operators will increase, carrying out economic work near the network. Near the property Umzārnieki, a reconstruction and reconstruction of the low-voltage overhead line is planned over 1 km

To improve the supply of electricity to customers in Garkalne County, rebuilding the power grid is done at Upesciems. from Makstenieki to Balozi, the 20-kV overhead line is rebuilt to 3.5-km cable and a new transformer station is under construction and a 0.2-km cable line is under construction [19659005]. In the Olaine district, this year, the rebuilding of the secondary voltage network is underway, as power lines are supplying several thousand customers. In the area between Stopini and the A4 Baltezers-Saulkalne motorway 1.5 km, a 20 kV overhead line will be dismantled, which will be rebuilt in 1.9 km cable. In Olaine district, Jāņupe, ST will build a new transformer station and rebuild the medium voltage line. for the cable lines in the length of 1.2 km

It is planned to rebuild the power grid in the district of Kekava this year in Ķekava, Gaismas street. In the building of the Ķekava district municipality and at the House of Culture at the same time as the reorganization of the parking provided by the municipality, ST will restore a low voltage network of 2 km and rebuild the transformer station. One of the most important projects will be carried out along the A7 motorway, where it is planned to renew and rebuild a 4.6 km medium voltage aerial cable line between Dzērmcelmiai and Dzimtmisa Iecava. During the reconstruction work, it is planned to build a new substation, a low voltage line of 100 m and install a remote-controlled control switch in the network, allowing ST personnel to remotely control the power grid and make interruptions. Remotely controlled power switches ensure that in the event of a fault, only the faulty power line is cut, but not the entire power line, so ST can immediately cut the lines. electric by reducing the customers' power time. But at Berzminni and on the ship's property this year, the rebuilding of the transformer station is underway.

The STO plans to implement three projects this year. Reconstruction work is already under way between Acioni and Ulbroku, where the medium-voltage line is rebuilt over a cable line 1.7 km away and a new low-voltage line is being built over a distance of 0.3 km, while Ulbroka ST builds a new transformer station, restoring the average voltage. Power lines 0.6 km long and 0.2 km of low voltage power lines. In order to improve the electricity supply of the inhabitants of Mucenieki, in the vicinity of the village, a medium voltage overhead line of 2 km long will be rebuilt in cable and a new transformer station will be built, improving the quality of service provided to 450 customers. when a medium voltage overhead line of 20 kV was transformed on a 0.7 km cable line, 0.5 km of low voltage cable line was built and a new transformer station was rebuilt and built. The reconstruction of the Muuga Street power grid began last year, improving the supply of more than 2,000 customers. Currently, the city 's electricity network is separated from the power supply network of industrial enterprises located near Muuga Street. In addition, the reconstruction of the power lines was carried out simultaneously with the reconstruction of the Muižas street, which was carried out by the municipality. Timely coordination of planned projects can lead to mutually acceptable solutions, coordinate activities, make efficient use of administrative resources, reduce overall project costs and reduce project lead times. # 39; execution. The reconstruction of the power grid was also completed on Gaujas Street, where 0.8 km of medium voltage overhead line was dismantled from Ozols to Ūbeļu Street and to build a new transformer station in Gaujas Street in order to Ensure a safe power supply. Reconstruction of the power grid continues from Lilastes to Duanezer, where the medium voltage A1 Baltezers-Ainaži line is rebuilt in 4.7 km long cable and a new transformer station is under construction and to Ilicone where low voltage power supply and overhead lines 1

In order to strengthen the reliability and quality of electricity supply of Ropazi customers, this year the reconstruction of the power grid is carried out in Tumšupė, where 4.2 km low voltage overhead power lines are rebuilt into cables improving the supply of more than 150 customers. safety and quality. In Zaķumuiza, the low-voltage overhead line is rebuilt 0.5 km away, while to protect the medium voltage network from damage caused by wood or tangled tree branches in the power lines, the power line between the properties of Liepsalas and Valtersala, of a length of 1.7 km, are being rebuilt in insulated cabling, and a new transformer station should be built during these works. The reconstruction of the electricity grid is expected to start this year in Ropaži, where it is planned to dismantle the long-lived medium and low voltage electricity grid in Ziedu and Bērzu Street. As part of the project, ST will build new medium voltage cable lines 1.3 km long and 1.1 km of low voltage cable lines. The reconstruction of the power lines has already been completed this year between Lielkangari and Vavrokrogs, where two new substations have been built, the medium voltage line of 20 kV has been restored to 500 m and the low voltage lines have been converted into lines of 5 km. Work was also completed in the vicinity of Purići, where a new transformer station was constructed, the medium voltage line renewed at 1.4 km and the low voltage line 0.4 km long

[ad_2]
Source link