Work at Hidroituango partially suspended



[ad_1]

A new turnaround took the execution of the Ituango hydroelectric project, following the order to suspend all activities related to the construction, filling and operation of the reservoir , issued by the National Authority for Environmental Permits (Anla), in Resolution 820 of 1 June.

It states that the suspension does not imply the implementation of the monitoring and surveillance plan, nor the work implemented from the contingency, generated since April 28 after the obstruction of auxiliary drifting tunnel by a landslide

The measure, which is of a preventive nature, will be maintained until the Hidroituango Company complies with a series of conditions, such as the hiring of employees. National or foreign experts, an opinion on the current conditions of stability and future operation of the hydroelectric project.

As stated by Anla in the resolution, the determination was made with the aim of avoiding that, with the future development of the project, additional unforeseen impacts could be generated which could cause more risky situations for environmental protection assets and impacts since April 28th.

The resolution imposes a series of burdens on the builder of the project. It must provide enough information to the Anla that allows to have scientific certainty as to the existence or not of risk conditions that may affect the environment. This information must be provided by experts who have no links or have participated in any stage of the project. Similarly, Anla asked Corantioquia to verify compliance with the imposed preventive measure, against which no remedy is required.

The administrative order specified that this preventive measure will be lifted only during the technical verification of the excess of the facts or

"Therefore, there is no fixed deadline for the validity Preventive measures of this administrative act, without prejudice to the legal obligation of the company to comply with the measures or orders given in the minor law.In a press release, EPM replied that she had been informed of the administrative act of Anla on Thursday afternoon.It indicated that the resolution temporarily suspended the regular activities not related to the eventuality and that the national authority maintained the environmental license in

"According to this measure, EPM must continue to carry out the actions it has carried out. This administrative act will be valid until an expert delivers an opinion on the present and future stability conditions of the infrastructure of the main works, "he said.