North / South line officially open after construction of fifteen years NOW



[ad_1]

The opening at the Central Station followed after a speech by Mayor Femke Halsema

Subsequently, the few hundred guests took the first metro to Noord Station, where another thousand of The guests were waiting for them. In the subway, members of the Netherlands Chamber Orchestra, who played Schubert's Unfinished, were on the way

Halsema said in his speech that the North Line / South brings people together. & # 39; & # 39; The new line offers opportunities but also much asked the city and the Amsterdammers. Amsterdam had to learn expensive lessons with sweat and tears, lessons that we should not take away, "she said.

Halsema mentioned the construction of the subway line that did not go smoothly. In 2002, it was estimated that the metro would be operational for the first time in March 2011. The delivery date was postponed several times, until early April it was decided that the subway line officially opened in July.

Commitment

The NorthSouthline brings people together, said Amsterdam Mayor Femke Halsema at the opening of the subway line. "The line connects old neighborhoods with new hot spots," said the mayor. & # 39; & # 39; North and South meet and can make a new commitment. & # 39; & # 39;

Halsema also spoke of the deaths of two people during construction, a staff member and a motorist who received a sheet piling on his car. "Thousands of pages have been written," the mayor looked back. "There have been debates for hundreds of hours … On the why of the North / South line In the dark corridors, in the mud, for years the man and the power were working, he There were daring pieces, there were technological delights, there were stories of heroism, tears flowed – of sorrow and joy.

Sagging

The project was delayed in the construction of the line and bankruptcies of construction companies, and several times a number of buildings on the Vijzelgracht in Amsterdam

In 2002 the budget was estimated at 1.4 billion euros, which then increased to 3.1 meters euro iljard

Insufficient coordination

Previously, it was still unclear whether the Amsterdam subway was going to roll the 22nd of July. Experts ruled early this year that much needed to be done before the subway could drive again.

In this way, the organizations involved would not be sufficiently in harmony with each other. According to the organization of travelers De Maatschappij Voor Beter OV, early failures could not be excluded, but there is too little alternative to public transport in the city.

However, the parties in question decided in April that they had confidence in the new subway line.

Alternative

The North / South line must link Amsterdam Noord to the South and offer an alternative to the growing automobile traffic in the capital.

Currently, a trip between the two districts lasts 31 minutes. With the new metro line, this trip takes sixteen minutes. The metro will run ten times an hour.