Elektrownia Ostrołęka C. There is a contract for the implementation of a large investment



[ad_1]

  In the photo, the president of Enea, Mirosław Kowalik, the energy minister Krzysztof Tchórzewski and the president of Energa Arkadiusz Siwko
Fig. PAP / Tomasz Waszczuk

In the photo, the president of Enea, Mirosław Kowalik, the energy minister Krzysztof Tchórzewski and the chairman of Energa Arkadiusz Siwko

The power plant. Ostrołęka, of which Energa and Enea are partners, has entered into a contract with the consortium GE Power and Alstom Power Systems. Ostrołęka C. Power Plant The value of the contract is over 6 billion gross PLN

– I am happy that the contract is signed. I hope the construction will start soon. Tchórzewski stressed that the block will be built using the most modern technologies and that for the east of Poland is the biggest investment since the 1990s. "Tchórzewski stressed that the block will be built using the technologies the

The conclusion of the contract does not equate to the acceptance of a start-of-work order (NTP) .This, as reported by the PAP, should be published before the December auction for the electricity market.At least this results from the statement of the president of Enea Miroslaw Kowalik

See also: Morawiecki during the exhibition: coal is the basis of our energy, we do not want to give up

On July 6th, the general meeting of shareholders of Elektrownia Ostrołęka sp. agreed to enter into a contract with the consortium of GE Power and Alstom Power Systems as an enterprise general editor for Elektrownia Ostrołęka C. Partners of Elektrownia Ostrołęka sp. there is Energa and Enea, each with 50%. shares

The bids for the construction of the Ostrołęka C power station were opened at the end of December 2017. The lowest price was offered by China Power Consulting Engineering Group – 4.849 billion gross PLN. The GE Power consortium and Alstom Power Systems offered a gross price of PLN 6.023 billion; and the Polimex-Mostostal Consortium and Rafako – PLN 9,591 billion gross. In April of this year the Ostrołęka Power Plant selected a consortium of GE Power Sp. Z oo In addition, at the end of June, Polimex-Mostostal concluded a letter of intent with GE Power concerning the cooperation in the construction of the Ostrołęka C power station. On their basis, the parties have expressed their intention to conclude a subcontracting contract. the following options: construction work, delivery of steel structures and assembly of steel structures. In addition, the parties may, as a separate arrangement, cooperate in the field of design work and other services and deliveries required for the project.

As previously stated, a high efficiency plant of about 1000 MWe, for supercritical steam parameters, will be burned. made of stone with the use of the most modern and ecological technological solutions.

Do you have news, a photo or a video? Send us an e-mail via historiasie.wp.pl

  ISB

[ad_2]
Source link