The Directorate General of Highways and National Highways (GDDKiA) signed an agreement with Polaqua for the construction of a 17-kilometer section of the A1 motorway from the border of the province. – to Czstochowa Pnoc for PLN 596.5 million, submitted to the Ministry of Investment and Development (MIR)
"C is the last fragment of the A1 motorway in the province, which has not yet had a selected contractor.This will mean that the section of nearly 17 kilometers will be ready in 2022. In addition to the road, the Mykanw will be built, the contract value is 596.5 million zlotys ", We read in the release.
Episode for which contract signed today with the entrepreneur, is part of a larger project – the construction of the A1 motorway from Tuszyn (around odzi) to Czstochowa To the north, which is already in the voivodeship, the section is taken from the road to Radomsko, which is currently in the tender phase, and south-east the construction of roads to Czstochowa Blachownia, reminiscent of the station
We expect that EU funding will rise to nearly e PLN 2 billion We are waiting for the request for co-financing from the road authority. The practice is that the request reaches us after the conclusion of contracts with contractors of particular sections. we will be able to sign the financing agreement in the first half of 2019, "said the Deputy Minister of Investment and Development Witold Sowik, quoted in the release
After the construction of the section Tuszyn – Czstochowa border crossing with the Czech Republic in Gorzyczki.It is about 600 kilometers, summarized in the communique
In a separate statement, GDDKiA recalls that A1 from the Tuszyn road to the Czestochowa ring road Of a length of about 81 km will have a value of about 3.7 billion (including: construction works, property compensation, surveillance) .It is divided into 5 sections
– Odc. At wz Tuszynzze Piotrkw Trybunalski South, about 15.9 km
On 7 June, the most advantageous offers of the consortium Budimex and Strabag (PLN 478.9 million) were selected, pre-auction in progress President's call for tenders from the Office of Public Procurement, after the completion of the contract (July / August)
– Ep. B, Piotrków Trybunalski Pudnie-Kamieki, about 24.2 km
the consortium: Przedsibiorstwo Budowy Drg i Mostw Kobylarnia and MIRBUD (PLN value 687 million), after 10 days and no cancellation, the tender documents will go to the prior check of the President of the Public Procurement Office (lasts about 30 days), after conclusion of the contract)
-Odc. Kamiesk-Radomsko C, about 16.7 km
It concerns four offers (from about 573.1 million PLN to PLN 655.4 million), the call for tenders is finalized, we will shortly indicate the most advantageous offers (expected signing of the contract at the beginning of the boil)
-Odc. D Radomsko -gr. province, about 7 km
On July 12, the company INTERCOR Technical Services Company received the best business offer (value 338.3 million PLN), after 10 days without cancellation, the documents call Tenders will be forwarded to the President of the Public Procurement Office. 30 days), after its completion the contract was signed (late August)
-Deep. E gr. province. dzial -w. Rzsawa, about 16.9 km
On May 16, the most advantageous offers were withheld and the president of the OPP, on July 23, was fired. signature of a Polaqua implementation contract (approximately 596.5 million)