There is a contract for the next section of the S61 expressway. He will be ready in three years



[ad_1]

The S61 expressway, at Ostrów Mazowiecka of S8, is the Polish part of the international Via Baltica road, which eventually has its own country with the Batien States – and precisely Warsaw with Tallinn in Estonia.

Wana was signed for the project and construction of the next section of S61. This time it is about 20 km to Podlasie, between Wysokie and Raczki. Budimex will take over the contract, and the contract amounts to more than PLN 484 million The completion of the construction works and the availability of drivers to the section is scheduled for 2021

 s61 from s61 high Raczek to: Ministry of Infrastructure

S61 almost already in "robot"

According to GDDKiA, out of 13 sections programmed S61 (about 214 km in length), only 3 have not signed contracts yet. There are episodes straw Zachd – Kolno (about 13 km), Szczuczyn – Ek Poudnie (about 23 km) and Ek Poudnie – Wysokie (about 23 km). However, entrepreneurs have already been selected for all these sections. As the managing director adds, the contracts for these last two episodes will be signed after the end of the current control of the President of the Public Procurement Office. The contracts for these three sections will amount to approximately $ 1.9 billion.

A section of S61 (Raczki – Beltway Slider) is used, the remaining 9 have a total length of about 142 km and umw values ​​of about 3.3. billion, is being executed

Below, the "construction status" of all sections of S61, for GDDKiA:

1. Podborze-niadowo, of about 19,5 km length

in execution, RUBAU POLSKA and CONSTRUCCIONES RUBAU Spain,

is worth about 479 million PLN, contract at 30/01/2018, commissioning of the fourth quarter of 2020.

2. Miodowo, Warsaw, about 17 km

in the process of execution, POLAQUA, worth about PLN 380 million, contract on February 9 2018, commissioning of the fourth quarter of 2020

3. Pole South West West, about 7.2 km

in progress, MOTA ENGIL Central Europe,

d. a value of about 218 million PLN, agreement 21.12.2017, commitment in Q4 2020

4. oma Zachd – Kolno, about 13 km

TOTO companies were selected (unsigned contract) ,

of a value of about PLN 525.6 million, commissioned for the second half of the year 2021

5. Kolno – Stawiski, about 16.5 km

being implemented, STRABAG, worth about 288 million zlotys, contract on 31/10/2017, setting up fourth quarter service of 2020

6. Stawiski – Szczuczyn, about 18 km

in the process of execution, BUDIMEX, worth about 342 million PLN, contract as of 31/10/2017, commitment in the fourth quarter of 2020

7. Szczuczyna II Road, approximately 6.6 km

being implemented, POLAQUA, D & # 39, a value of about PLN 75 million, contract on 26/05/2017, delivery in the spring of 2020

8. Szczuczyn – Ek Poudnie, about 23 km

BUDIMEX companies were selected (unsigned contract),
of a value of about 672 million PLN, commissioned in the third quarter of 2021

9. Ek Poudnie – Wysokie, about 23 km ( with S16 to Eku)

a consortium was selected: TRAKCJA PRKI, Mostost Warszawa, Przedsiebiorstwo Eksploatacji Ulic and Mostw Biaystok, (unsigned contract),
worth PLN 686 million, expected delivery in the third quarter from 2021

10. Wysokie – Raczki, about 20 km

in execution, BUDIMEX, worth PLN 484 million, contract 4.07.2018, devotion after 2021

11. Raczki – around the Slider, about 13 km

in use, BUDIMEX, implementation of the district of Augustow,
worth $ 659 million, delivered in 2014

12. The bypass of the Slider, about 12.8 km

being executed, BUDIMEX, worth about PLN 300 million, contract 29/09/2015, commissioned in the spring of 2019

13. Suwaki – Budzisko, about 24.2 km

in progress, IMP RESA PIZZAROTTI, worth approximately 605 million PLN, contract 6.06.2017, put into service after 2020

 Expressway S61 - Mileage Expressway S61 – Mileage to: GDDKiA

The entire route S61 is to be ready in the third quarter of 2021, but most sections must be ready by 2020

There are also missing sections of the S8 road, ie the Via Baltica road from Warsaw (Powzkowska) to the end of the Ostrów Mazowiecka ring road. This year drivers drive the missing sections of Wyszków to the Ostrów Mazowiecka belt. total cost of construction S8 Warsaw – Ostrw Mazowiecka is about 4 billion.

Read these: great lights for drivers. Money goes to a 200 km fast track S61 Via Baltica

***

Rafa Masna: For three years we spent 15% on wages. profit, the rest on investments [NEXT TIME]