The first kilometer of the Stara Pazova-Indjija highway was laid



[ad_1]

He began to lay the upper machine of the track on the long seven kilometer section between Stara Pazova and Indjija

  jpg

This section is part of the direction Stara Pazova – Novi Sad, where RZZD Internešnl performs the works of the annex no 3.2.

The annex provides for the construction of a two-lane railway, two viaducts, two galleries, 19 bridges and a viaduct or subway, as well as only 36 small

In addition, a new Beška station with trails will be built, Inđija, Sremski Karlovci and Petrovaradin stations with trails will be reconstructed, as well as the position of Karlovac Vinogradi.

Work on the section Stara Pazova – Indjija started in March 2018

The cleaning of the fields has already been carried out, the access roads to the construction machines were built, the old elements of the way and the elements of the network of contacts were dismantled, as well as external devices S S. for drainage of water, drainage and platform

More than 170 people and 111 building units and railway machines are currently engaged in the project

The result of the implementation will be the increase in speed to 200 km / h. increase rail capacity and level safely

The value of this contract, signed in November 2017, is about 248 million US dollars.

The completion of the works is scheduled for 2021.

In addition, as part of the implementation of the annex no. 3.1. with the basic contract, RZZD Internešn continues to carry out active work on the construction of two large facilities, which are not in Serbia – the tunnel Čortanovci and a three-kilometer viaduct in the blue part of the Danube