Working on track for a transparent MRT link at Orchard Station, Transport News & Top Stories



[ad_1]

When the Thomson-East Coast Line (TEL) section of the Orchard MRT station will open in 2021, commuters will enjoy a seamless transfer between the NSL and TEL lines, thanks to a passage under the boulevard. Orchard.

The Land Transport Authority (LTA) yesterday revealed how this is being built without disrupting heavy traffic along Orchard Boulevard or inconveniencing commuters using the Orchard MRT station.

A method called pipe roofing is used for the first time. a MRT project here. It is to create an underground pipeline of interlaced steel pipes 1.2 m in diameter around the tunnel.

This allows for operation without compromising the road or buildings, according to Mr. Henry Foo, the LTA's deputy group. Director of TEL and the Cross Island Line.

Micro tunneling machines were deployed to dig a tunnel into the ground in order to install the pipes. They are about eight times smaller than the usual ones used for MRT tunneling. The use of interlocking hoses also prevents misalignment and breakage of hoses.

Before the construction of the canopy, work was done to stabilize the soil and prevent water from escaping into the tunnel.

Mining was completed last December and a permanent concrete tunnel is being built.

Mining and Underlying is under the MRT Orchard station to connect the two platforms. a "great feat of engineering," said Mr. Foo.

It is made using special drilling machines, which can drill in all directions in a confined space. Work must be done gradually so as not to disrupt railway services.

Work will also be done at the Orchard MRT station to add escalators, an elevator and a stairway to connect to the TEL platform.

Detailed planning and close coordination were in progress with the 39 SMRT transport operator in order not to disrupt the operations of the station or annoy the commuters, adding that most of this work can only be done after hours of operation. connect the TEL section of the interchange station to the Ion Orchard and Wheelock Place shopping centers.

Minister of State for Transportation Janil Puthucheary, who visited the site yesterday, said that this work demonstrated innovation and ingenuity TEL

Network Expansion Singapore's railway is not without its problems, he adds.

"As our network becomes denser and longer, consideration of what we need to make the next changes, because we do not want to interfere with what we have today (the existing lines of MRT), "he said.

When completed, the 43km TEL will extend from Woodlands North to Sungei Bedok

It will open in stages beginning next year, starting with three stations – Woodlands North, Woodlands and Woodlands South.

ST GRAPHICS