The pumping station temporarily loses electricity and heavy rainfall exceeds the S & WB drainage system



[ad_1]

Heavy rains Sunday have exceeded the capabilities of the drainage system, according to the Office of Sewers and Waters. The agency also announced that pumping station 7 Marconi and I-610, which protects Lakeview, Mid-City and Gentilly, briefly stopped operating around 5 am. says the teams responded by setting up a backup generator on the site. At 6:00 am this pump was returned to service. Between 5:15 and 6:15 am, more than two inches of rain fell in less than an hour over much of the city. This amount of rain has exceeded the drainage system. The SWBNO reports that the highest recorded rainfall rate was about three inches during this hour at the 5th drainage pumping station in the lower 9th district. At some point, between 23:00 and 23:00. According to SWBNO statistics, Saturday and 6 am, no less than five inches fell in some parts of the city. Most of the widespread street flooding that took place was eliminated in less than two hours, officials said. The teams plan to continue to evaluate this storm and the reaction of the drainage system. According to the WWB, 115 out of 120 pumps were available during the storm. The agency said it had generated more than 42 megawatts of electricity to run the city's drainage pumps. The utility has the capacity to produce more than 72 MW if needed. "It is important to note that not all drainage pumps can operate simultaneously because such a force would overflow downstream channels.Draining stations have redundant pumps in case equipment in service suffers a loss SWBNO is going to continue to gather information and look for any opportunities to continue to improve its response to rain events. "The S & WB said the event today showed some system improvements drainage, but some areas took much longer to drain including: the area bounded by Canal Boulevard, West End Boulevard, City Park Avenue and Filmore Avenue; Broad Street and Orleans Avenue Corridors, Banks Street Corridor, Franklin Avenue at I-610 / I-10 Overpass, Napoleon Avenue, from Claiborne Avenue to Broad Street, Corridor St. Bernard Avenue, St. Claude Avenue, from Elysian Fields Avenue to the 9th Ward Lower and General de Gaulle's Corridor and Wall Boulevards. "My administration is laser focused on the entire infrastructure and on stormwater management in particular," said Mayor LaToya Cantrell. "As we tackle problems head on, we use data and experience to live better with water." If you notice a clogged catch basin or insufficient drainage area, you are encouraged to call 311.

The heavy rains on Sunday have exceeded the capabilities of the drainage system, according to the Office of Wastewater and Sanitation.

The agency also announced that pumping station 7 At Marconi and I-610, which protects Lakeview, Mid-City and Gentilly, briefly lost power around 5am.

SWBNO reports that the teams responded by setting up an on-site emergency generator. At 6 o'clock in the morning, this pump is put back into service.

Between 5:15 and 6:15 am, more than two inches of rain fell in less than an hour over much of the city.

This amount of rain has exceeded the drainage system. The SWBNO reports that the highest recorded rainfall rate was about three inches during this hour at the drainage pumping station 5 in the 9th district.

At one point, between 11 pm According to SWBNO statistics, Saturday and 6 am, no less than five inches fell in some parts of the city. Most of the widespread street flooding that took place was eliminated in less than two hours, officials said.

The teams plan to continue to evaluate this storm and the reaction of the drainage system.

According to SWBNO, 115 out of 120 pumps were available during the storm. The agency said it had generated more than 42 megawatts of electricity to run the city's drainage pumps. The utility has the capacity to produce more than 72 MW if needed.

"It is important to note that not all drainage pumps can operate simultaneously because such a force would overflow downstream channels." Drainage stations have redundant pumps in case material problems in service would encounter problems during rainy periods. ", says SWBNO.

"SWBNO will continue to collect information and look for opportunities to continue to improve its response to rain events."

The S & WB said today's event highlighted some improvements to the drainage system, but some areas took much longer to drain, including: the area bounded by Canal Boulevard, West Boulevard, City Park Avenue and Filmore Avenue; Broad Street and Orleans Avenue Corridors, Banks Street Corridor, Franklin Avenue at I-610 / I-10 Overpass, Napoleon Avenue, from Claiborne Avenue to Broad Street, Corridor St. Bernard Avenue, St. Claude Avenue, from Elysian Fields Avenue to the 9th Ward Lower, General de Gaulle Boulevard and Wall Street corridor.

"My administration is laser focused on the overall infrastructure and on stormwater management in particular," said Mayor LaToya Cantrell. "In the face of our problems, we use the data and the experience to live better with water."

If you notice a fouled catch basin or a poorly drained area, we invite you to call 311.