Emirates Airline cuts flights to 111 destinations …



[ad_1]

Mustafa Abdul Azim (Dubai)

Emirates plans to cut its flights to 111 destinations around the world on its flight schedule from April 16 to May 30, 2019, due to the maintenance and modernization of the southern runway of Dubai International Airport. The security, service and capacity of the stairs, which lasts 45 days.

Etihad's operating program for this period shows that the airline has selected approximately 1,000 scheduled flights scheduled to be suspended during the upgrade period after the airline has studied the application for all destinations to identify the least affected destinations Focusing on destinations served more than one day, as well as destinations with reduced demand when upgrading the runway, for s & # 39; 39 ensure that passengers are not confused.

According to schedule, flights to about 13 selected destinations were reduced to two flights per day for a single flight, reduced to one destination with four flights per day to three flights, and the number of flights to eight reduced destinations of three flights per day Only two flights instead of three, while weekly flights to a selected number of destinations will be reduced from one to three flights per week, depending on the operating conditions of each destination.

Emirates experienced the same situation during the maintenance of the Dubai International Airport in 2014, which lasted 80 days, during the maintenance of the first runway, from May 1 to May 31 and the second from June 1st to July 20th. For the airport during this period only one track. The Dubai Airports Corporation announced at the end of February its plan to close the 45-day south terminal of the Dubai airport from April 16 to May 30 to carry out a comprehensive upgrade to improve security, service and l & # 39; energy. The southern runway (12R-30), which monitors the end of its life, must recalibrate its surface, replace the ground lighting of the airport grounds and infrastructure. Support The renovation of the runway includes approximately 60,000 tonnes of asphalt and 8,000 cubic meters of cement to reinforce and recalibrate the runway surface and closed trails the Rh.

Dubai airports take advantage of this opportunity to install main cables of a length of 800 km and replace more than 5,500 slope lighting lamps with modern, economical and environmentally friendly alternatives.

According to Dubai Airports, the period from April 16 to May 30, 2019 was chosen to complete the development of the runway as it usually experiences a decline in passenger traffic due to the period of seasonal calm, with the aim of reducing Impact on the service. The airlines have reduced their operations at the Dubai International Airport due to the significant reduction in capacity resulting from the availability of a single runway for operations.

As in the 2014 Northern Runway Modernization Program, the Dubai International Airport will be an alternative to accommodate regular scheduled flights, as well as charter, charter and private aircraft.