The North Hospital does not come from the headlines: the Hospital Association (KAV) has invested on the site 610,000 euros in a well, which has never been achieved. Depending on the city, an outside evaluator made a mistake.

In 2012, KAV wanted to use well water to heat the North Hospital. MA 58 (Water Law) approved the project, and MA 45 (Viennese waters) did not report any concerns in a report. Thus, the KAV has invested in the planning and construction of electricity and piping, as reported by the "Kronen Zeitung"

but nothing should come out of the well. Vienna Water Management GmbH found that the well threatened a nearby contaminated site. According to the newspaper, the approved water consumption should have been reduced from 300 liters per second to 30 liters per second. So the well project was off the table. According to the newspaper, a total of 610,000 euros was poured.

  North

ORF.at/Christian Öser

The North Hospital of Floridsdorf

According to MA 58, an expert had made mistakes

The Court of Auditors criticized Report on KH North that MA 45 and 58 had not integrated water management for contaminated sites in a timely manner. According to MA 58, a legally sworn expert has been deceived.

"However, the remarks of the external evaluator proved to be inaccurate on one point, so that negotiations followed to reduce the withdrawal until the issuance of the MA 58 Water Attorney mandates – none effect on the neighboring rights of use of water – were met again.To meet these requirements, the amount of groundwater allowed to be extracted had to be reduced.C & # 39; was the candidate but then for the project planned too low, "he said in a statement from the MA 58 against wien.ORF.at.

City check "possibility of appeal"

Upon request to health advisor Peter Hacker (SPÖ) on the case: "The city is considering the possibility of an appeal." Only in March had ordered an energetic in the construction of North KH caused a stir. He had been instructed to put an "energy protection ring" around the hospital for 95,000 euros. The prosecution has also opened investigations – more on that in the energy in North KH: the prosecutor 's audits.