Union with Stanilov at the lowest price for the tunnel "Zheleznitsa"



[ad_1]

Сн. Archive

<! –


Archive

->

A union headed by Stanilov gave the lowest price for the construction of the 2 km tunnel "Zheleznitsa", which is part of the Struma road. The prices of the candidates were opened more than seven months after the opening of tenders

The price of the merger "AM Struma – tunnel Zheleznitsa", including "Stanilov" EOOD, "Ingstroyengineering" EOOD and "Logistics 21 "is more than 175.5 mln. , excluding VAT, announced the Agency of Road Infrastructure (RIA). The technical evaluations of the candidates are not communicated. This is in Tory Experience for Tunnel Tunnel Builders' Choice, located on midway between Blagoevgrad and Krupnik on the Struma Highway. The previous auction failed at the time of the official government of Ognian Gerdjikov. The reason was the missing file of one of the bidders – Glavbolgarstroy. In the present case, the prosecutor 's office lodged a complaint against the commission member, Stefan Gaytandjiev, but did not have official information about what is happening in the case

. the tunnel at three o'clock and shortened the implementation time of the installation. The goal is to build it by the end of 2023, by which time it will financially end the current EU programming period. The project is financed by the operational program "Transport"

Five price offers for the road in front of the tunnel

The first batch concerns the construction of about 720 m of road at the gate north of the tunnel. He has an estimate of a value of 33.5 million BGN without VAT.

Seven candidates submitted bids for her. On five of them today, the price offers were opened

The lowest price was the unification "ORS-M" – nearly 26.7 million from BGN excl. VAT. The company registered under the Law on Obligations and Contracts includes the OOD "Moscovult" and "ORS Infrastructure" OOD.

Here are the open price offers for Lot 1:

  • Patstroy-92 – Mostremont, with participants Patstroy 92 and Mostremont 97 Ltd. – BGN 32 554 154.34

  • With the participation of GBS Infrastructural Construction AD, Glavbolgarstroy AD and Glavbolgarstroy International EAD – 29 985 345,00 BGN

  • "Kalistratov Grup" OOD – BGN 28,447,832.31 excl. VAT

  • "Hydrostroy AD – 33 125 154.37 BGN excluding VAT

  1. " ORS – M ", with participants" Mostconsult "OOD," ORS Infrastructure "OOD – 26 697 927.86 BGN without VAT

    built

    Four tunnel price offers

    The second separate article concerns the construction of the 2.28-kilometer tunnel serving the road to the south portal and helicopter site, with an indicative value of 194.3

    For him, most of the offers were submitted – 13. Only four of them were open today.The lowest is the amount of union "AM Struma – Tunnel Zheleznitsa "- more than 175.5 million levs without VAT

    Here are the offers of open prices for lot 2:

  • Highway "Struma" Direction-OP2: Tunnel Zheleznitsa, with participants Glavbolgarstroy JSC, GBS Infrastructure Construction JSC – 191 479 153.57 BGN [

  • The badociation "Tunnel Zheleznitsa", with the participants "Euro Alliance Tunnel" AD, "ISA-2000" EOOD, "Putproekt EOOD" – 184 168 742.24 BGN [

  • "AM STRUMA – Tunnel Zheleznitsa" with participants Stanilov EOOD, Ingstroyengineering EOOD, Logistics 21 EOOD – BGN 174 524 519.06

  • "AM Struma Tunnel 2018", with participants "GP Group" JSC, Global Construction Ltd and Via Plan EOOD – 185 370 370. 37 BGN

The term for the execution of design and construction is 1060 calendar days

Five price offers for 1.4 km

The third batch relates to the construction of a road of 1.4 km – from km 369 + 000 to km 370 + 400. Its value indicative was 22.1 million BGN excluding VAT

The candidates for its construction were eight, and five were admitted at the opening of the price proposals. The lowest price is for PST Group EAD – 18.4 million BGN

Here are the open price quotes for lot 3: Patstroy 92 AD – 18 658 616.86 BGN

  • "Construction & Construction GBS infrastructure "AD – 21 196 979.07 BGN

  • " Strimon "DDZ, with participants" AutoMagistrali-Cherno More "AD and IK KEI Bulgaria Engineering Consultants EOOD – 19 848 378.82 BGN

  • Association" Intervianova ", with participants BGNova AD, Interprom EOOD, Engineering Group-04 EOOD, Hydro Consult Engineering EOOD – BGN 21,960,000

  • EAD – BGN 18,442 297.40 Excluding VAT

  • The term h and the execution of design and construction is 660 calendar days

    * Note: All prices are excl. VAT