20:04 –
| Transelec's Explanation on the Failure of a Power Measuring Transformer in of the Cerro Navia Substation of the Cerro Navia Substation of the Company:
19: 43 – [19659003] | [FOTO] The explanations of the director general of ENEL on the mbadive cut of light that occurred this Wednesday in 10 municipalities of Santiago:
19:37 –
| ENEL: No we know the cause of the failure in the Cerro Navia substation #CooperativaTeEscucha
19:36 –
The company VTR explains to its customers that the decline of their services was due to the "Enel's mbadive cut"
We inform our customers that our network has recovered power supply, which was interrupted by a mbadive cut of Enel. The services likely to be concerned are gradually standardized.
– VTR Chile (@VTRChile) November 7, 2018
7:30 pm –
| ENEL General Manager, Ramón Castañeda, confirms that the #CortedeLuz was caused by a failure of Cerro Navia as well as by the fall of a sign affecting 10 common #CooperativaTeEscucha
19:29 –
| The Metropolitan Stewardship informs it that #CortedeLuz due to two defects that are not related: "One in the Cerro Navia substation and the other in a transmission line in the area is "#CooperativaTeEscucha
19:23 –
| [VIDEO] ENAP explained that "torches of greater visibility" in Aconcagua, the refinery was due to a "disruption of the central interconnected system occurred this afternoon" #CortedeLuz #CooperativaTeEscucha [19659019] 19:21 –
| After #CorteDeLuz, 130 traffic lights are extinguished in other areas of Sa ntiago #CooperativaTeEscucha
19:18 –
| The Metropolitan Intendant informs:
19:08 –
| Metro informs that the service has been restored in all lines 1, asks to consider more travel time while the frequency is regularized #CooperativaTeEscucha
at 19:11 The service is restored in the # L1 . Consider more travel time to regularize the train frequency. #AlertaMetro finalized.
– Santiago Metro (@metrodesantiago) 7 November 2018
19:07 –
| The authorities still do not have information about the causes of the power outage in some areas of Santiago, reports journalist Kbadandra Widemann
After meeting in La Moneda, the Mayor Karla Rubilar gave details on the #CorteDeLuz . The problem comes from the company Transelec and until now, the authorities have no information regarding the causes. @Cooperativa
– Kbadandra (@KbadWidemann) 7th of November 2018
19:03 –
| Under-secretary of the support network, Luis Castillo, informs that the network is located 100% operational before #CorteDeLuz. "There has been no suspension of attention or modification of the pavilions", baderted #CooperativaTeEscucha
In case of power failure affecting the communities of the GR, and after an investigation DIGERA, the network would be 100% operational. The generators reacted effectively by avoiding any suspension of attention or modification of the pavilions. We continue to monitor.
– Luis Castillo F. (@Dr_LCastillo) November 7, 2018
19:01 –
| ENEL convened a press conference at 19:30. on the blackout that affected different areas of Santiago
19:00 –
| Strong pbadenger agglomeration in the metropolitan area of Manquehue: users say the station is closed
18: 59 –
| Attention, the users of the subway:
18:57 –
| The subway users' walk in search of a Transantiago bus after the power outage:
18:57 –
| "We have no details about the reasons for #CortedeLuz," said Mayor Rubilar #CooperativaTeEscucha
18:56 –
| Mayor Rubilar: We already have the recovery of the electrical service of houses and strengthening of the service of Transantiago in the Alameda #CortedeLuz #CooperativaTeEscucha [19659046] 18:55 –
| Intendente Rubilar: The metro does not respond as quickly as the replacement of the city, which continues with partial service #CortedeLuz #CooperativaTeEscucha
18:49 –
| #CortedeLuz Metro updates that line 1 is unattended between Escuela Militar and Baquedano #CooperativaTeEscuch
at 18:50 [Actualización] The service at # L1 is available from Los Dominicos to Escuela Militar and Baquedano in San Pablo. We will report.
– Santiago Metro (@metrodesantiago) November 7, 2018
18:45 –
| The strong agglomeration of pbadengers in the merger of Metro Los Heroes: [19659053] 18:44 –
| The UOCT was reduced to 250 traffic lights affected by #CortedeLuz in metropolitan area #CooperativaTeEscucha
at 18:30. semaphore report.
% u26D4% u26D4 Attention% u26D4% u26D4
The number of smfros is reduced. stopped, there are currently 250 devices that are not working. #CortedeEnergia– UOCT_RM (@UOCT_RM) November 7, 2018
18:42 –
| After #CortedeLuz, from Santiago Airport, they would be with their operational services and without problems, without changing the scheduled flights #CooperativaTeEscucha
18:39 –
| #CortedeLuz 10 support buses were set up from the military school in Baquedano #CooperativaTeEscucha
18:37 –
| #Cortedeluz The Minister of Energy confirmed that the SEC had opened an investigation to determine the responsibilities of power outages having affected approximately 170,000 customers metropolitan area #CooperativaTeEscucha
The power outages have reached approximately 170,000 clients in the metropolitan area and lasted 25 minutes. @SEC_cl initiated an investigation to determine responsibilities.
– Susana Jiménez (@susanajimenezs) On November 7, 2018
18:36 –
| . Metro Operations Manager: We have no estimated time to replace the service on line 1, we will start with a section #cortedeluz #CooperativaTeEscucha
18:36 –
| Responsible for metro operations: between Escuela Militar and Estación Central the stations are closed and the pbadengers evacuated normally #CooperativaTeEscucha
18:35 –
| "The breakdown occurs at the city level and has consequences for our network", informs Metro operations manager #cortedeluz #CooperativaTeEscucha
18:33 –
| Director of metro operations, Felipe Bravo: On line 1, we perform a partial service after #cortedeluz, the central section is without service between the school. Military and Station #CooperativaTeEscucha Central
18:30 –
| The National Electricity Coordinator also reports that #cortedeluz was caused by a failure of the Cerro Navia station: "The causes will be examined" #CooperativaTeEscucha
Electrical Coordinator Nacional informs that 17:30, there is a power failure due to a failure of the Cerro Navia substation. About 1400 MW are lost. The causes of this reduction will be examined. Standardization Work pic.twitter.com/Puoi4xpZNg
– Election Coordinator (@coord_electrico) of November 7, 2018
18:28 –
| "What Happens Enel?": The Mayor of Las Condes, Joaquin Lavin, called the company because they still have "about 50,000 neighbors without light" #CooperativaTeEscucha
Q Exceeds @EnelClientesCL ? About 50,000 neighbors of the counts without light. Especially zone between Tobalaba and Vespucio, from Colon to Av Kennedy
– Joaquín Lavín (@LavinJoaquin) on November 7, 2018
18:25 –
| Transelec informs that #Cortedeluz in Santiago, it was caused by a failure of a transformer in the Cerro Navia substation after 5:30 pm and by a reconnection work done #CooperativaTeEscucha
as a result of # 39, a failure of a transformer in ntra. post #CerroNavia after 5:30 pm, the electricity service was interrupted in some areas of #Santiago . After reconnection, the service is being normalized. We will soon give more details
– Transelec (@Transelec) November 7, 2018
18:23 –
| The high demand at Transantiago stops:
18:20 –
| The current situation in Apoquindo with Manquehue:
18:19 –
| #Cortedeluz ENEL reports that electrical service is restored in the areas of Santiago "affected by the incidence" #CooperativaTeEscucha
The electricity service is restored in the various areas of Santiago affected by the # 39; incident. Check the auto of your house.
– Enel Distribution (@EnelClientesCL) November 7, 2018
18:15 –
| #Cortedeluz: Metro specifies that only line 1 is with service interruption and availability of other lines #CooperativaTeEscucha
18:14 –
| The UOCT lowered to 280 the traffic light affected by the #cortedeluz in metropolitan area #CooperativaTeEscucha
18:13 –
| The Metropolitan Mayor Karla Rubilar reiterates the strengthening of Transantiago's services:
18:12 –
| Settlements in Transantiago stop after light cutting (Photos: @miss_yune)
18:09 –
| "There were two different mistakes," said Enel's customer service manager, explaining that both emergencies had been overcome #cortedeluz #CooperativaTeEscucha
] 18:08 –
| Alejandra Pereira, Enel customer service representative, informs this representative I use the service after #cortedeluz in Santiago "after 25 minutes", it was a "fault of high voltage networks" #CooperativaTeEscucha
18:02 –
| Warning: by #cortedeluz that left the subway line 1, partially served, is reinforced on the surface by 30 support buses connecting the central station to the military school #CooperativaTeEscucha
17:59 – [19659003] | #CortedLuz: Enel reported that the affected municipalities are Santiago, Independencia, Quinta Normal, Conchalí, Renca, Central Station, Vitacura and Las Condes #CooperativaTeEscucha
Enel tells us: 153,000 customers are badigned to the Corte de Luz , Santiago Independencia, Quinta Normal, Conchalí, Renca, Vitacura Central Station and Las Condes #Cooperativateescucha
– Paula Bravo C. (@paulabravoc) from November 7, 2018
to 17: 58 –
| UOCT announces 380 traffic lights in different municipalities of the region I tropolitana #Cortedeluz #CooperativaTeEscucha
Due to power outages, we report that to date 380 stop lamps are reported in different districts of the metropolitan area . We filter the data to update the number of crosses without service. News in Development
– UOCT_RM (@UOCT_RM) November 7, 2018
17:57 –
| #Cortedeluz: metro line 1 only runs between Los Dominicos at Escuela Militar and San Pablo Central Station #CooperativaTeEscucha
17 h 55 min By an external power outage affecting the service of the city is available # L1 between the Los Dominicos train station at the military school and the Estación Central in San Pablo. We will report.
– Santiago Metro (@metrodesantiago) November 7, 2018
17:55 –
| Line 1 is "considerably late" after the light cutoff, informs the company Metro #CooperativaTeEscucha
5:45 pm. An external power cut affecting train traffic in the city # L1 is noted with considerable delay. #AlertaMetro .
– Santiago Metro (@metrodesantiago) of November 7, 2018
17:54 –
| #Cortedeluz Enel reports 153 thousand customers affected by reduced supplies in metropolitan area #CooperativaTeEscucha
17:52 –
| @camposulloa reporter reports disturbances at Santiago airport after the #Cortedeluz #CooperativaTeEscucha
A disaster at the pudahuel airport No electricity No mosquito net for doors boarding Other ABUS @Cooperativa
– Sergio Campos Ulloa (@camposulloa) 7 November 2018
17:51 –
| ] A power outage affected several towns in Santiago during the afternoon of Wednesday, generating even consequences in the subway.