Monday at 17:00, the deadline to show interest for the second auction organized by RAE for renewable energy plants (wind and photovoltaic) is complete.
Application processing will be completed on December 10th for December 10th and will be completed for each project category (photovoltaic power up to 1 megawatt, photovoltaic power from 1 to 20 megawatts and wind turbine from 3 to 50 megawatts) . The auction aims to increase the penetration of renewable energy sources into the energy balance while limiting the costs directly or indirectly borne by consumers.
The bidding is done at a starting price set by RAE decision, whereas they are governed by a competition rule according to which the power finally awarded will be at the required level to reach a participation of at least 75%. power auctioned. For example, if the investment interest in a category is formed, after verification of vouchers to 150 megawatts, the power to auction will be set at 85.72% in order to meet the 75% rule .
According to the relevant decision, participation in the competitive procedures is the existence of an badociation agreement or a definitive offer in force, as well as a letter of guarantee, a clause introduced to allow bidders to participate in completed projects with a short construction schedule. RAE stated that "if, prior to the expiration of the final connection offer, a request for an badociation agreement had been submitted in good time and in due form to the 39, competent administrator, then, in accordance with the existing framework, the final connection offer remained in effect and therefore the project can continue the licensing process and submit a request to participate in the competitive process. "
The competition procedures by category are as follows:
Category I: Photovoltaic plants up to 1 MW. The maximum power auctioned is 94 MW, from € 81.71 per megawatt.
Category II: Photovoltaic power plants from 1 to 20 MW. Maximum auction power of 100 MW, from € 71.91 per megawatt hour.
Category III: Wind power plants from 3 to 50 MW. Maximum auction power of 229 MW, starting price from € 79.77 per megawatt hour.
Source: RES
[ad_2]