Still an open land, this is the Cijago Section III toll



[ad_1]

Depok – The construction of the Cinere-Jagorawi toll road (Cijago) continues today. The toll road consists of 3 sections covering section I from Jagorawi to Raya Bogor, section II from Raya Bogor to Kukusan and section III from Kukusan to Cinere.

Section I of the Cijago toll road has been operational since 2012. Section II is nearing completion, but ground problems persist, particularly in the Kukusan area or connection with Section III.

So, how is the project in section III? Based on monitoring detikFinanceFriday afternoon (26/10/2018), the project of section III of the Cijago toll road had not yet started. Seen from the direction of Kukusan, there is a small amount of excavated ground.After the search, only visible trees, etc., are residents. The workers also did not seem to be continuing their work in Section III. Heavy equipment commonly used for the construction of toll roads is also invisible.
PT Secretary General Jasa Marga Tbk said Agus Setiawan, Cijago Toll was managed by PT Translingkar Kita Jaya. He said that since Jasa Marga is only a minority shareholder, the toll policy was entrusted to PT Transindo Karya Investindo, the Kompas Gramedia Group as a majority shareholder.

"JM (Jasa Marga) is a minority, a policy of the group Kompas Gramedia, majority shareholder," he said about the progress made in detikFinance, Friday (26/10/2018.

At the same time, there remain 25 fields not yet free for section II, ie about 1.2 ha. The land belongs to 19 residents.

PT Hutama Karya stated that it was only a contractor in Section II. Hutama Karya depends on the land settlement process for the completion of the toll road.

"Yes, we do not know when the publication is only in progress, and if it is completed, it will be done immediately," said Secretary General Hutama Karya M Fauzan.

(hns / hns)