Hanool Nuclear Power Plant [연합뉴스]
Hanool 2 Nuclear Power Plant (9.5 million kW pressurized light water reactor type) It resumed its development in 16 days.
Unit 2 of the Hanwool Nuclear Power Plant was shut down automatically during the 12th test of the turbine protection system valve. Indeed, the "rupture plate", which blocks the humidity of the steam pbading through the high pressure turbine, has worked abnormally.
Korea Hydro & Nuclear Power Corp. caused micro-damage during the repair of the rupture plate, and the parts were damaged by high pressure during the test process. Yuan Yuan replaced the bursting plate.
The nuclear power station inspects all breaks with the same function and replaces four with new ones to avoid their recurrence.
The Hanool 2 nuclear plant, which resumed its development in the morning, will reach 100% of its production at 10 am on the 29th.
Park, Kwangsoo, [email protected]