Electricity Lebanon clarifies electricity supply in the Nabatieh region



[ad_1]

EDL said in a statement that he "was commenting on protests and statements regarding the decrease in electric recharge, particularly in Nabatiyeh and its villages." As the current capacity of the network is about 2000 megawatts, The factors that led to the reduction of the electric recharge in the different Lebanese regions outside Beirut, namely:

1- In its book no. 6262 of June 21, 2018, the Foundation requests that the third free ship be connected to the main Zahrani power plant. ] To inject about 236 megawatts on the implementation of the public network of the Resolution of the Cabinet of Ministers No. 84 of 21/5/2018, so that the energy of the 220KV, including Nabatiyeh and its villages, will be used for this energy. Beyond the will of the company, which currently produces only 35 megawatts. "

and added: "2 – Maintenance required of temporary and within a specified period (one week) on the first group of gas from the factory Deir Ammar badociated with the steam group during the last week which has led the suspension of this group on Monday production cut production to the lowest level until last Saturday, noting that this work is part of the rehabilitation of the boiler of this group, which began on 26/3/2018 is expected to end later this week and add another 70 megawatts on the steam group network, improving electric charging in various areas, including Nabatiyeh and its villages. "

3. EDL has budgeted for the year 2018 on the basis of the price of a barrel of oil between 60 and 65 US dollars and has requested a contribution from the state to pay the deficit of 39. Fuel purchase worth 2800 billion pounds The 2018 general finance law sets a flat rate for the sale of electricity in Lebanon since 1994. With the steady rise in oil prices since the beginning throughout the year, the Foundation 's Board of Directors has pbaded several resolutions calling on the official authorities concerned to increase this contribution. For the past few years, it is by putting k the company had been waiting for seven months the response of the people concerned: she had to stop one of the two production groups of the Baalbek factory ( 30 megawatts) to save fuel, and she was unable to extract energy. "The delay in deciding the issue of the distribution service providers, including the service provider in the southern suburbs of Beirut and South and South by the Council of Ministers for a year and a half, has halted investments in the distribution sector Note that these projects started with the approval of the Maj The Ministers extended this company in its decision n ° 70 of 26/4/2018, in which it is planned to deal with all "strangulation" in the coming period, which helps to ensure greater electrical stability in these areas. "

And the political struggles that the institution most often victimizes, are working to ensure electricity supply is also stable in all Lebanese regions, given the technical capacities available in each region. It also confirms the need to set up new factories to meet the growing demand for energy by completing the implementation of the Electricity Sector Policy Document approved by the Council of Ministers in June 2010. and the 2017-2030 Production and Transport Guidelines specifying the investments to be made in these sectors. Over the next 12 years. "