According to Vidmantas Grušs, director of Litgrid's transport network department, the postponement of the start of the repair is not a delay, but for a reason, he baptized the test of joints and fires in Sweden . Given the increased risk of fire, the contractor must coordinate the threat plan with the municipalities in order to obtain the necessary work permits, said Wednesday the press conference .
ABB, a Swedish company, was producing a cable company, but the Danish company NKT took over the repair work.
ABB transferred his company (…) to the subcontractor for the excavation work of NKT – "Kauno tiltai" – V. Grušas
On Wednesday, it was reported that the coupling should have They are subject to change from August 16th to October 28th. Previously, it was announced that work will begin on July 30 and will continue until October 10.
Repairs, which will replace 116 ground couplings: in Lithuania – 22 and in Sweden – 98.
550 million. NordBalt was launched at the end of 2015 at 453 kilometers and the connection was launched at the beginning of 2016.