On Friday, two planes landed at the new terminal. Delta Air and South Africa Airways landed at Terminal Three with pbadengers from the United States for operational testing of the new terminals.
According to GACL, the two airlines voluntarily offered the use of their aircraft as part of the initial operational tests
The first large-scale simulation exercise for Terminal 3 is scheduled to take place on Saturday with approximately 1000 aircraft volunteers.
They have all been informed of the different roles they will play.
Number of Pbadengers
The new terminal should accommodate up to five million pbadengers a year, with a potential for expansion of up to 6.5 million pbadengers.
At rush hour, the terminal will have the capacity to handle up to about 1,250 pbadengers. A fully automated baggage handling system will also process 3,500 bags at the time.
The facility will also house a large commercial and commercial area, three trade shows, six fixed lines and seven airlifts expandable to eight, as well as a parking space that can accommodate: manage over 700 cars. The airport expansion supports the government's ambition to make Ghana a regional aviation center
Details
KIA Terminal 3 is a monumental feat. It has five levels spread over 45,000 square meters and has a parking space for 700 cars.
It has six contact points for Code E aircraft and two remote stations. At departure level, it has 56 check-in counters, 30 pbadport control centers and eight security lanes
At the arrivals level, it has 24 immigration counters, four automatic teller machine [expandable to eight] and four recovery devices. 19659002] The terminal is equipped with a fully automated baggage handling system to handle the baggage of destination and transit at 3,500 bags per hour.
It was built and built by the Turkish construction company Mapa Construction MNH Holdings.