Remedies the need for space at the Center for Commercial and Industrial Education:
Since Thursday, July 5, the newly constructed section 5 is ready to move in.
"This is a day of joy for the Industrial and Industrial Training Center (GIBZ) train," writes the Baudirektion in a press release on July 5. For Thursday, the director of the building Urs Hürlimann was able to hand over the new building to the economic director of his colleague in the government, Matthias Michel. With the acquisition of the new section 5, the GIBZ can once again offer all educational offers under one roof on the Baarerstrasse.
Today, GIBZ offers basic education for about 27 different professions. He also manages the courses of the Higher Technical College of Technology and Design (HFTG) and the Professional Baccalaureate. In particular, the encouraging development in these areas has led to an acute shortage of space, so that the GIBZ has had to outsource various offers in recent years. "More than 1300 young people start an apprenticeship each year in the canton of Zug, half of whom visit the GIBZ," says the rector of the Beat Wenger school in the press release. Building director Urs Hürlimann adds: "According to the analysis of available space, the GIBZ lacked about 17 units or about 1580 square meters to fully fulfill the educational mandate of a school. cantonal professional for trades, industry and health. planned and the cantonal council approved the necessary credit, is further from the message.
After about two years of construction, tract 5 with six floors is realized. "We are happy to hand over this successful work to the school and thereby strengthen the educational site Canton Zug," said government councilor Urs Hürlimann in the press release
New Independent Building
The Complex existing school with Sectors 1 to 4 a new building (lane 5) has been added. The new independent building creates optimal structures for the needs of space and allows great flexibility for future needs. Spatially, the new wing occupies the last remaining free space between the residential building of the V-Zug pension fund and the GIBZ 4. According to school management, it previously served as an outdoor sports ground, but it was very little used, because physical education was mainly done in the triple gymnasium
Five years ago, the cantonal council approved a loan of 25.71 million francs. "The decision of the Cantonal Council at the time to approve an additional hull for the hull 5 of the GIBZ was looking towards the future," says Hürlimann in retrospect.
Because: Shortly before the start of construction of Section 5, it became clear that the demand for nursing education and restoration continues to increase. Therefore, the Baudirektion to the Cantonal Council immediately requested the complete extension of the sixth floor and the parliament also approved the application. This extension costs 580,000 francs, but can be supplemented in the total credit already approved by the Cantonal Council.
"Today, I note that with the expansion of the sixth floor, all health professions can be taught both practically and theoretically at GIBZ," Hürlimann continues in the statement Press. And the rent of the outside premises disappears. Basic education education activities in health service and health and social professional maturity can be coordinated effectively and economically. (red)