The company submitted a 38.51% rebate for projects in RS
CPFL Geração submitted a lower offer of 38.51% compared to Aneel's maximum PCR of 55 111 735, R $ 00 for projects located in Rio Grande do Sul that will require investments of R $ 348.9 million. The final ERR amounted to 33.888 billion rand. Lot 11 includes:
-LT 230kV Osório 3 – Gravataí 3 C1, with 66 km;
-LT 230 kV Porto Alegre 8 – Porto Alegre 1 (metro), with 3.4 km;
] -LT Botanical Garden 230 kV – Porto Alegre 1 (subway), 4 km;
-SE 230 kV Osório3;
-SE 230/69 kV Porto Alegre 1 (isolated from SF6 – Nova) – 3 x 83 MVA;
-SE 230/138 kV Vila Maria – 2 x 150 MVA;
-Thermos of LT in 230 kV between SE Osório 3 and LT Osório 2 – Lagoa dos Barros, C1, with 2 x 4 km
-Therks of LT in 230 kV between SE Vila Maria and LT Pbado Fundo – Nova Prata 2, C1 and C2, with 4 x 1 km