[ad_1]
So Paulo, 28 – Sterlite won lot 4 of the auction which will take place on Thursday 28th at the headquarters of B3 in So Paulo, offering an annual allowance of 25 R $ 7 million for construction and construction. Project, which corresponds to a disbursement of 57.16% compared to the maximum ERP established for the R $ 60,002,250.00 project.
voice with competitor ISA Cteep, who even offered a write-off of 53.97 %%. During the first stage of the competition, eight bidders submitted bids for the lot, including companies such as Energisa and CPFL Energia
This second batch won by the Indians, which led to the largest project offered up to the end of the year. here Lot 3, 1.2 billion reais.
Lot 4 consists of a 500 kV transmission line between Campina Grande and Joo Pessoa, at Paraba, with 127 km extension, a 500/230/69 kV substation at Joo Pessoa and section sections 230 KV Goianinha – Mussur II;
According to the National Electric Power Agency (Aneel), the work is aimed at securing the Metropolitan Regio of Joo Pessoa
. Investments are estimated at R $ 366,847,037.42 and are expected to generate 815 direct jobs. The entrepreneur has 54 months to start the commercial operation of the company.
(Luciana Collet)
Source link